Views: 0 Author: Site Editor Publish Time: 2025-04-17 Origin: Site
Project Operating Conditions: 70000m³/h
Project Concentration: 500mg
In response to the government's implementation acceptance of environmental protection equipment upgrading and transformation. Project operating conditions: 70,000 m³/h, zeolite rotor +RTO system, spray painting exhaust gas, concentration 500mg. The equipment selection for the project is based on the concentration and on-site working conditions. Currently, the equipment is operating stably and the discharge at the outlet also meets the local discharge standards.